| Provisional cost estimate for power plants | ||
| Item description | 150 MW | 400 MW |
|---|---|---|
| Combustion turbine | $29 m | $77 m |
| Steam generator | $ 15 m | $40 m |
| Steam turbine | $ 15 m | $41 m |
| Feedwater | $ 13 m | $ 35 m |
| Cooling water | $ 5 m | $ 14 m |
| Electricals | $ 10 m | $ 26 m |
| Instr & control | $ 4 m | $ 12 m |
| Buildings etc. | $ 5 m | $14 m |
| Site improvements | $ 5 m | $ 13 m |
| Other off-site costs | $ 7 m | $ 18m |
| Total | $ 108 m | $290 m |
| Benefits from Recommended Best Local Alternatives | |||||
|---|---|---|---|---|---|
| Member States | Energy shortfall assumed (GWh/Yr) | Unit Cost of Production($ / kWh) | Savings/Unit($ / kWh) | Total annual savings ($m/year) | |
| Most efficient present Ops possible | Recommended best local alternative | From best local alternatives | |||
| Gambia | 384 | 0.158 | 0.117 | 0.041 | 15.8 |
| Guinea | 486 | 0.158 | 0.117 | 0.041 | 20.0 |
| Guinea Bissau | 127 | 0.158 | 0.117 | 0.041 | 5.2 |
| Liberia | 370 | 0.158 | 0.117 | 0.041 | 15.2 |
| Sierra Leone | 417 | 0.158 | 0.117 | 0.041 | 17.2 |
| Benin | 237 | 0.158 | 0.068 | 0.049 | 21.3 |
| Burkina Faso | 477 | 0.174 | 0.084 | 0.049 | 43.0 |
| Ghana | 2.642 | 0.158 | 0.064 | 0.053 | 249.5 |
| Mali | 412 | 0.189 | 0.084 | 0.065 | 43.5 |
| Senegal | 573 | 0.158 | 0.084 | 0.033 | 42.7 |
| Togo | 153 | 0.158 | 0.064 | 0.053 | 14.4 |